Fourteen classrooms, two corridors and the staff room renovated over the summer break and handed back clean, safe and inspected a week before the new term.

Client
Day school, primary and secondary
Duration
7 weeks, summer holidays
Students reading papers at their desks in a bright classroom

The brief

The school had one window to renovate a whole classroom block: the summer holidays. Rooms had to be quieter, brighter and easier to keep clean, and nothing could run into the first week of term.

How we worked

We surveyed and ordered materials before term ended so work could start the day the pupils left. Crews ran in parallel across both floors, and the toilet blocks were waterproofed and tested early so tiling never held up the programme.

  • Weekly progress meetings with the bursar and site manager
  • Every finish chosen for durability and low odour
  • Final clean and safety check one week before term

The result

Classrooms that sound calmer and feel lighter, toilets that no longer leak into the corridor below, and a staff room the teachers actually use.